Sarona Tunnels, Tel Aviv

Project

Financial scope:45,000,000 NIS
Execution period:4 years
Work commissioned:Yahel Engineers LTD

Mission: Execution of an 800 meters traffic tunnel including electromechanical and Communications systems

Electricity: Execution of electricity systems, including high and low voltage facilities, generators

Communications: CCTV, Building Control, Security, Access Control, Communications and Telephony, construction of a 10 Km long optical fiber infrastructure

Air conditioning: ventilation facilities, 10 blowers 180 kWh, 25 smoke removal blowers

Plumbing: Sprinklers consisting 72 Deluge elements, pumping rooms for fire control and water pressure increase, drainage pump rooms